GHPS OLD Anekal – Room 1 and Room 2 Construction Status – Completed

Stage 4 Status : Completed

Stage 3 Status : Completed

1. Deshuttering and Preparation for inside plastering (Deshuttering already done)

2. Inside Electrical work

3. Door and Windows Fixing

4. Inside wall Plastering

5. Flooring and Putty work

6. Grill Fixing and Other Fabrication work

Stage 2 Status – Completed

1. Roof concreting work done
2. Curing and ponding work done
3. Preparation of parapet wall done
4. Exterior plastering preparation 
5. Ordering door and windows

Stage 1 Status – Completed

1. Site Preparation & Material Procurement
2. Chipping and Demolition work
3. Wall Construction Work
4. Lintel Casting
5. Wall Construction for Roof Level